Search here for Tutorials

If the Data is different in your question, please send your questions to homeworksolutionsnow@gmail.com. The questions will be answered at the same price.

The standard cost summary for the most popular product of Excelsior Products Company is shown as follows

The standard cost summary for the most popular product of Excelsior Products Company is shown as follows
 
P8-7 Materials and labor variance analyses
 
P8-7 The standard cost summary for the most popular product of Excelsior Products Company is shown as follows, together with production and cost data for the period.
Standard Cost Summary
Materials:
2 gallons of liquid lead@$2.00/gallon . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             $4.00
2 gallons of varnish@$3.00/gallon . . . . . . . . . . . . . . . . . . . . . . . . . . . .                      $6.00    $10.00
Labor:
1 hour@$12.00/hour. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                 12.00
Factory overhead:
$1.00 per direct labor hour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                  1.00
Total standard unit cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                              $23.00
Production and Cost Summary
Units completed during the month . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .               9,000
Ending units in process (one-fourth completed) . . . . . . . . . . . . . . . . . .                     2,000
Gallons of liquid lead used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             21,000
Gallons of varnish used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .            20,000
Direct labor hours worked . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .            10,000
Cost of liquid lead used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .            41,160
Cost of varnish used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .           60,000
Cost of direct labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .           117,000
 
One gallon each of liquid lead and varnish are added at the start of processing. The balance of the materials is added when the process is two-thirds complete. Labor and overhead are added evenly throughout the process.
 
Required:
1. Calculate equivalent production. (Be sure to refer to the standard cost summary to help determine the percentage of materials in ending work in process.)
2. Calculate materials and labor variances and indicate whether they are favorable or unfavorable.
3. Determine the cost of materials and labor in the work in process account at the end of the month.
4. Prove that all materials and labor costs have been accounted for.
 
TUTORIAL PREVIEW
Problem 8-7
1.
Equivalent Production
Units
Materials:
Completed during the month
9000
Equivalent units in ending work in process
1000
Total
10000
 
 File name: P8-7 Excelsior Products.xls File type: xls PRICE: $6