Cash flows are forecasted on a project. It uses internal rate of return rule to accept or reject projects. Should this project be accepted if the required rate of return is 12%.
Co = -10,000; C1=0, C2 = +7,500; C3= +8,500.
In addition to the answer can you provide the formula?
SOLUTION PREVIEW
Year CF PV factor @12% Present
Value PV factor @22% Present value
0- 10,000 1 -10000 1 -10000
0- 10,000 1 -10000 1 -10000
1 0 0.893 0 0.82 0
2 7,500 0.797 5977.5 0.672 5040