On February 1,2007, Nance Contractors agreed to construct a building at

On February 1,2007, Nance Contractors agreed to construct a building at a contract price of $6,000,000. Nance estimated total construction costs would be $4,000,000 and the project would be finished in 2009. Information relating to the costs and billings for this contract is as follows:                              SOLUTION

                                                                      2007               2008                2009
Total costs incurred to date                            $1,500,000      $2,640,000      $4,600,000
Estimated costs to complete                           2,500,000        1,760,000        -0-
Customer billings to date                                2,200,000        4,000,000        5,600,000
Collections to date                                         2,000,000        3,500,000        5,500,000

Instructions
Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2007.

Percentage-of-Completion Completed-Contract
Gross Profit Gross Profit
2007 2007
2008 2008
2009 2009